To the Campion Skating Community, 9/7/23
With skating season fast approaching, we are very excited
about the renovation underway at Campion Rink.
Opening day is scheduled for September 30th and it is
important for all skaters and their families to recognize that the
first phase of construction is still ongoing.
What does this mean?
It means we will have two, possibly three locker rooms available
initially. We will know more as opening day gets closer.
It also means that the only bathrooms available will be in the
locker rooms, with the public lobby bathrooms opening soon.
Construction will continue to take place during the day and my
guess is it will be ongoing well into October before the first phase
is complete.
For the short term, entry and exit will be very near where the
old entrance existed until the new front entry in the new lobby is
complete. We will set up chairs behind the goal similar to our Covid year
for any overflow of skaters until all four locker rooms are
complete.
The finished product is going to be great and one we will all be
proud of!
We appreciate your patience as we finish up phase one
of the Renew Campion project.
Jeff Graham – General Manager